Subject: Diagnosis of DD150 reprocessing
Nicola.Zaccheo@lngs.infn.it
Date: Mon Mar 27 2000 - 11:13:16 EST
This is a report on the processing of DD150
From: AXPGS3::MACROUSA "LNGS US MACRO group" 26-MAR-2000 21:19:27.31
Subj: Start COPY of FIRST (#1) file of DD150 (RUN015112) Selected CPU:3/DISK:9
From: AXPGS3::MACROUSA "LNGS US MACRO group" 27-MAR-2000 00:51:48.19
Subj: Done COPY of LAST (#30) file of DD150 (RUN015138) Selected CPU:3/DISK:9
Download from tape to disk lasted ~ 2.5 hrs.
From: AXPGS3::MACROUSA "LNGS US MACRO group" 27-MAR-2000 00:51:53.38
Subj: Submitted FIRST (#1) ZEB2RAW job of DD150 (RUN015112) Selected CPU:3/DISK:9
From: AXPGS3::MACROUSA "LNGS US MACRO group" 27-MAR-2000 03:22:08.68
Subj: Submitted FIRST (#1) MR MONITOR job of DD150 (RUN015112) Selected CPU:3/DISK:9
Conversion of ZEBRA to RAW lasted ~ 2.5 hrs.
Then the processing of the RAW RUN files started. It lasted ~ 8.5 hrs
DD150 is now completed. It took 2.5+2.5+8.5= ~13.5 hrs.